Preconstruction estimating produces an early budget or conceptual estimate before construction documents exist, working from schematic drawings, a scope narrative, or comparable projects. K2E gives GCs a defensible early number so design decisions get made against a real budget instead of a guess.

The earlier a number exists, the more control you have over the outcome. We build conceptual and budget estimates in the design phase so you can steer scope and selections before the budget is locked.

What's included

  • Conceptual and rough-order-of-magnitude estimates
  • Budgets from schematic design or a scope narrative
  • Cost benchmarking against comparable projects
  • Updates as the drawings develop through design
  • Clear assumptions so everyone prices the same scope
Detached garage, 24 x 24 Sample estimate excerpt
Description Qty Unit Material Labor Total
Site prep and excavation 1 LS - 3,850 3,850
Concrete slab on grade 576 SF 4,320 3,168 7,488
Framing, walls and trusses 576 SF 7,200 5,760 12,960
Roofing, architectural shingle 14 SQ 2,380 2,940 5,320
Siding, fiber cement 1,120 SF 4,928 5,264 10,192
Overhead door and opener 2 EA 3,180 940 4,120
Electrical, rough and finish 1 LS 1,240 2,760 4,000
Subtotal, 7 of 34 line items 47,930