What's included

  • Your unit costs and your historical pricing
  • Direct line to your PMs and field staff
  • Consistent output that matches your house style
  • Overflow capacity through busy season
  • No headcount, no benefits, no seat to fill
Detached garage, 24 x 24 Sample estimate excerpt
Description Qty Unit Material Labor Total
Site prep and excavation 1 LS - 3,850 3,850
Concrete slab on grade 576 SF 4,320 3,168 7,488
Framing, walls and trusses 576 SF 7,200 5,760 12,960
Roofing, architectural shingle 14 SQ 2,380 2,940 5,320
Siding, fiber cement 1,120 SF 4,928 5,264 10,192
Overhead door and opener 2 EA 3,180 940 4,120
Electrical, rough and finish 1 LS 1,240 2,760 4,000
Subtotal, 7 of 34 line items 47,930

See the work before you commit